Project: Fast Link Telecommunication Towers, Jordan (4 Phases)

Client

:

Jordan Mobile Telephone Services  (Fastlink)

Starting Date

:

15/03/1995

Completion Date

:

31/12/1997

Project Value

:

US$ 9,058,523

As an active participant in the Jordanian Mobile Tele-communication Surge, MID Contracting has been the sole and exclusive contractor in installing, erecting, and commissioning Tele-Communication Towers for the benefit of the service provider in Jordan (Fast Link).

 

Thus far, the total number of cell sites built around 450 cells incorporated into 210 roof top sites and 240 green field sites, ranging in height from 6 to 60 m covering urban, rural and remote areas spreading all over the kingdom.


 

 

 

Project: O.F. Cable and Accessories to Link Jordan with Iraq, Jordan

Client

:

Jordan Tele-Communication Company (JTC)

Starting Date

:

01/2002

Completion Date

:

01/2003

Project Value

:

US$1,052,112

Trenching, O.F. laying, back filling, and commissioning of 199 km of optical fiber cables line to be connected to the National Grid running from Al Safawi to the Jordanian Iraqi Border, the project consists of all telecommunication and electrical and civil works leading to the handing over of total project (turn key basis).

 

Project: Construction & Implementation of IDEN Sites to NEWGEN, Jordan

Client

:

NEWGEN

Starting Date

:

01/11/2003

Completion Date

:

15/04/2005

Project Value

:

US $7

 

This project is for constructing, maintaining, and executing of (107) cell sites in Jordan, (Turn Key Job) including all needed works, and these cell sites vary between green field and roof top sites.

 

 

 